Project Details
This report breaks down the development cycle for the new EspressReport
product for the next year.  Development is displayed by task, and by
department.
Project Task
Projected Start
Projected End
1
Market Analysis
Jan 15, 2003
Mar 2, 2003
2
Concept/Plan Development
Mar 1, 2003
May 7, 2003
3
Product Development
Mar 28, 2003
Nov 14, 2003
4
GUI Development
May 2, 2003
Aug 22, 2003
5
GUI Evaluation/Testing
Jun 18, 2003
Sep 12, 2003
6
Alpha Version Release
Jul 12, 2003
Jul 12, 2003
7
QA Testing Phase 1
Jul 21, 2003
Aug 2, 2003
8
Fix Outstanding Alpha Bugs
Jul 24, 2003
Sep 14, 2003
9
Beta Version Release
Sep 18, 2003
Sep 18, 2003
10
QA Testing Phase 2
Sep 10, 2003
Oct 28, 2003
11
Fix Oustanding Beta Bugs
Nov 1, 2003
Dec 1, 2003
12
Box & Packaging Design
Sep 12, 2003
Dec 15, 2003
13
Product Collatoral Development
Aug 7, 2003
Oct 1, 2003
14
Final QA Testing
Nov 3, 2003
Dec 30, 2003
15
Final Release
Dec 20, 2003
Dec 20, 2003